Engine Mount for A wholesale group in West Africa
A wholesale group came to us with a engine mount programme for West Africa. The brief was ordinary and unforgiving at the same time: a fixed launch window, a landed cost that had to survive freight and duty, and a part that had to match an existing sample. This case records what was specified, what went wrong in sampling and how the bulk order landed.
The starting point
- A specification nobody had written down
- A supplier who changed material without saying so
- Packing that arrived crushed at the port

What was specified
| Part | Engine Mount |
|---|---|
| Client | A wholesale group |
| Market | West Africa |
| Volume | 10,000 pieces across 3 specifications |
| Base material | Polypropylene |
| Sampling rounds | 2 |
| Delivery window | 5 weeks from PO to ex-factory |
| Compliance | SGS |
How it was resolved
- The specification was rebuilt around Polypropylene and the tolerance locked before bulk.
- A pre-production sample was approved and kept as the golden reference.
- Production ran with in-line inspection and a mid-run photo report.
- Cartons were packed to the client's own barcode and ratio specification.
- Documentation shipped with the goods instead of after them.

Result
- 10,000 pieces delivered inside the 5-week window.
- Unit cost held within 4.5% of the original quotation.
- Inspection-related rejection stayed under 0.5%.
- The specification is on file, so reorders reproduce the approved sample.
What we would repeat
Fix the specification count early. Adding variants after production starts is the most expensive change a client can request.