Case Study: Control Arm Supply for a regional distributor in East Africa
Source:Case /
Time:2026-09-18
Control Arm for A regional distributor in East Africa
A regional distributor came to us with a control arm programme for East Africa. The brief was ordinary and unforgiving at the same time: a fixed launch window, a landed cost that had to survive freight and duty, and a part that had to match an existing sample. This case records what was specified, what went wrong in sampling and how the bulk order landed.
The starting point
- Inconsistent hardness between lots
- Lead time that slipped twice before bulk started
- A supplier who changed material without saying so

What was specified
| Part | Control Arm |
|---|---|
| Client | A regional distributor |
| Market | East Africa |
| Volume | 2,000 pieces across 6 specifications |
| Base material | Bronze |
| Sampling rounds | 3 |
| Delivery window | 10 weeks from PO to ex-factory |
| Compliance | IATF 16949 |
How it was resolved
- The specification was rebuilt around Bronze and the tolerance locked before bulk.
- A pre-production sample was approved and kept as the golden reference.
- Production ran with in-line inspection and a mid-run photo report.
- Cartons were packed to the client's own barcode and ratio specification.
- Documentation shipped with the goods instead of after them.

Result
- 2,000 pieces delivered inside the 10-week window.
- Unit cost held within 2.0% of the original quotation.
- Inspection-related rejection stayed under 1.0%.
- The specification is on file, so reorders reproduce the approved sample.
What we would repeat
Lock the material standard before sampling. Once the base changes, every downstream approval has to be redone and the calendar slips.
Planning something similar?
Share a sample or a drawing and we will quote against a written specification, not against a photograph.



