Case Study: Intercooler Supply for an agricultural cooperative in North Africa
Intercooler for An agricultural cooperative in North Africa
An agricultural cooperative came to us with a intercooler programme for North Africa. The brief was ordinary and unforgiving at the same time: a fixed launch window, a landed cost that had to survive freight and duty, and a part that had to match an existing sample. This case records what was specified, what went wrong in sampling and how the bulk order landed.
The starting point
- Premature wear on the first batch
- Packing that arrived crushed at the port
- A fitment that looked right on paper and failed on the bench

What was specified
| Part | Intercooler |
|---|---|
| Client | An agricultural cooperative |
| Market | North Africa |
| Volume | 5,000 pieces across 6 specifications |
| Base material | Tempered Glass |
| Sampling rounds | 3 |
| Delivery window | 5 weeks from PO to ex-factory |
| Compliance | REACH |
How it was resolved
- The specification was rebuilt around Tempered Glass and the tolerance locked before bulk.
- A pre-production sample was approved and kept as the golden reference.
- Production ran with in-line inspection and a mid-run photo report.
- Cartons were packed to the client's own barcode and ratio specification.
- Documentation shipped with the goods instead of after them.

Result
- 5,000 pieces delivered inside the 5-week window.
- Unit cost held within 3.0% of the original quotation.
- Inspection-related rejection stayed under 1.0%.
- The specification is on file, so reorders reproduce the approved sample.
What we would repeat
Fix the specification count early. Adding variants after production starts is the most expensive change a client can request.
Planning something similar?
Send the specification you are working to and we will confirm what we can match, what we would change and why.



