Case Study: Window Switch Supply for a spare parts retailer in the Middle East
Window Switch for A spare parts retailer in the Middle East
A spare parts retailer came to us with a window switch programme for the Middle East. The brief was ordinary and unforgiving at the same time: a fixed launch window, a landed cost that had to survive freight and duty, and a part that had to match an existing sample. This case records what was specified, what went wrong in sampling and how the bulk order landed.
The starting point
- Inconsistent hardness between lots
- A supplier who changed material without saying so
- Packing that arrived crushed at the port

What was specified
| Part | Window Switch |
|---|---|
| Client | A spare parts retailer |
| Market | the Middle East |
| Volume | 5,000 pieces across 2 specifications |
| Base material | PVC Coated Fabric |
| Sampling rounds | 2 |
| Delivery window | 10 weeks from PO to ex-factory |
| Compliance | ISO 9001 |
How it was resolved
- The specification was rebuilt around PVC Coated Fabric and the tolerance locked before bulk.
- A pre-production sample was approved and kept as the golden reference.
- Production ran with in-line inspection and a mid-run photo report.
- Cartons were packed to the client's own barcode and ratio specification.
- Documentation shipped with the goods instead of after them.

Result
- 5,000 pieces delivered inside the 10-week window.
- Unit cost held within 2.0% of the original quotation.
- Inspection-related rejection stayed under 0.5%.
- The specification is on file, so reorders reproduce the approved sample.
What we would repeat
Lock the material standard before sampling. Once the base changes, every downstream approval has to be redone and the calendar slips.