Case Study: Heater Core Supply for a wholesale group in East Africa
Heater Core for A wholesale group in East Africa
A wholesale group came to us with a heater core programme for East Africa. The brief was ordinary and unforgiving at the same time: a fixed launch window, a landed cost that had to survive freight and duty, and a part that had to match an existing sample. This case records what was specified, what went wrong in sampling and how the bulk order landed.
The starting point
- Packing that arrived crushed at the port
- A specification nobody had written down
- Lead time that slipped twice before bulk started

What was specified
| Part | Heater Core |
|---|---|
| Client | A wholesale group |
| Market | East Africa |
| Volume | 2,000 pieces across 2 specifications |
| Base material | ABS Plastic |
| Sampling rounds | 3 |
| Delivery window | 4 weeks from PO to ex-factory |
| Compliance | REACH |
How it was resolved
- The specification was rebuilt around ABS Plastic and the tolerance locked before bulk.
- A pre-production sample was approved and kept as the golden reference.
- Production ran with in-line inspection and a mid-run photo report.
- Cartons were packed to the client's own barcode and ratio specification.
- Documentation shipped with the goods instead of after them.

Result
- 2,000 pieces delivered inside the 4-week window.
- Unit cost held within 3.0% of the original quotation.
- Inspection-related rejection stayed under 0.5%.
- The specification is on file, so reorders reproduce the approved sample.
What we would repeat
Fix the specification count early. Adding variants after production starts is the most expensive change a client can request.
Planning something similar?
Send the part number, the annual volume and the target market, and we will come back with a specification and a sampling plan.