Case Study: Vacuum Hose Set Supply for an online marketplace seller in North Africa
Vacuum Hose Set for An online marketplace seller in North Africa
An online marketplace seller came to us with a vacuum hose set programme for North Africa. The brief was ordinary and unforgiving at the same time: a fixed launch window, a landed cost that had to survive freight and duty, and a part that had to match an existing sample. This case records what was specified, what went wrong in sampling and how the bulk order landed.
The starting point
- A supplier who changed material without saying so
- A specification nobody had written down
- Lead time that slipped twice before bulk started

What was specified
| Part | Vacuum Hose Set |
|---|---|
| Client | An online marketplace seller |
| Market | North Africa |
| Volume | 20,000 pieces across 4 specifications |
| Base material | Bronze |
| Sampling rounds | 2 |
| Delivery window | 6 weeks from PO to ex-factory |
| Compliance | E-mark |
How it was resolved
- The specification was rebuilt around Bronze and the tolerance locked before bulk.
- A pre-production sample was approved and kept as the golden reference.
- Production ran with in-line inspection and a mid-run photo report.
- Cartons were packed to the client's own barcode and ratio specification.
- Documentation shipped with the goods instead of after them.

Result
- 20,000 pieces delivered inside the 6-week window.
- Unit cost held within 4.5% of the original quotation.
- Inspection-related rejection stayed under 2.0%.
- The specification is on file, so reorders reproduce the approved sample.
What we would repeat
Fix the specification count early. Adding variants after production starts is the most expensive change a client can request.