Case Study: Mud Flap Supply for a government fleet in North Africa
Source:Case /
Time:2026-09-18
Mud Flap for A government fleet in North Africa
A government fleet came to us with a mud flap programme for North Africa. The brief was ordinary and unforgiving at the same time: a fixed launch window, a landed cost that had to survive freight and duty, and a part that had to match an existing sample. This case records what was specified, what went wrong in sampling and how the bulk order landed.
The starting point
- Premature wear on the first batch
- Lead time that slipped twice before bulk started
- A specification nobody had written down

What was specified
| Part | Mud Flap |
|---|---|
| Client | A government fleet |
| Market | North Africa |
| Volume | 5,000 pieces across 3 specifications |
| Base material | Semi-Metallic Compound |
| Sampling rounds | 4 |
| Delivery window | 5 weeks from PO to ex-factory |
| Compliance | IATF 16949 |
How it was resolved
- The specification was rebuilt around Semi-Metallic Compound and the tolerance locked before bulk.
- A pre-production sample was approved and kept as the golden reference.
- Production ran with in-line inspection and a mid-run photo report.
- Cartons were packed to the client's own barcode and ratio specification.
- Documentation shipped with the goods instead of after them.

Result
- 5,000 pieces delivered inside the 5-week window.
- Unit cost held within 4.5% of the original quotation.
- Inspection-related rejection stayed under 1.0%.
- The specification is on file, so reorders reproduce the approved sample.
What we would repeat
Lock the material standard before sampling. Once the base changes, every downstream approval has to be redone and the calendar slips.
Planning something similar?
Tell us the model, the fitment and the quantity and we will hold a production slot for you.