Case Study: Steering Rack Supply for an agricultural cooperative in West Africa
Steering Rack for An agricultural cooperative in West Africa
An agricultural cooperative came to us with a steering rack programme for West Africa. The brief was ordinary and unforgiving at the same time: a fixed launch window, a landed cost that had to survive freight and duty, and a part that had to match an existing sample. This case records what was specified, what went wrong in sampling and how the bulk order landed.
The starting point
- A specification nobody had written down
- A fitment that looked right on paper and failed on the bench
- A supplier who changed material without saying so

What was specified
| Part | Steering Rack |
|---|---|
| Client | An agricultural cooperative |
| Market | West Africa |
| Volume | 10,000 pieces across 3 specifications |
| Base material | Chromed Steel |
| Sampling rounds | 4 |
| Delivery window | 10 weeks from PO to ex-factory |
| Compliance | REACH |
How it was resolved
- The specification was rebuilt around Chromed Steel and the tolerance locked before bulk.
- A pre-production sample was approved and kept as the golden reference.
- Production ran with in-line inspection and a mid-run photo report.
- Cartons were packed to the client's own barcode and ratio specification.
- Documentation shipped with the goods instead of after them.

Result
- 10,000 pieces delivered inside the 10-week window.
- Unit cost held within 3.0% of the original quotation.
- Inspection-related rejection stayed under 1.5%.
- The specification is on file, so reorders reproduce the approved sample.
What we would repeat
Approve a pre-production sample made from the actual bulk material. Substitute material behaves differently in service.
Planning something similar?
Send the part number, the annual volume and the target market, and we will come back with a specification and a sampling plan.