Case Study: Leaf Spring Supply for a wholesale group in West Africa
Source:Case /
Time:2026-09-18
Leaf Spring for A wholesale group in West Africa
A wholesale group came to us with a leaf spring programme for West Africa. The brief was ordinary and unforgiving at the same time: a fixed launch window, a landed cost that had to survive freight and duty, and a part that had to match an existing sample. This case records what was specified, what went wrong in sampling and how the bulk order landed.
The starting point
- A supplier who changed material without saying so
- Documentation that arrived after the container shipped
- A specification nobody had written down

What was specified
| Part | Leaf Spring |
|---|---|
| Client | A wholesale group |
| Market | West Africa |
| Volume | 50,000 pieces across 6 specifications |
| Base material | Stainless Steel |
| Sampling rounds | 4 |
| Delivery window | 6 weeks from PO to ex-factory |
| Compliance | DOT |
How it was resolved
- The specification was rebuilt around Stainless Steel and the tolerance locked before bulk.
- A pre-production sample was approved and kept as the golden reference.
- Production ran with in-line inspection and a mid-run photo report.
- Cartons were packed to the client's own barcode and ratio specification.
- Documentation shipped with the goods instead of after them.

Result
- 50,000 pieces delivered inside the 6-week window.
- Unit cost held within 1.5% of the original quotation.
- Inspection-related rejection stayed under 1.5%.
- The specification is on file, so reorders reproduce the approved sample.
What we would repeat
Keep one accountable owner on both sides. Most delays come from hand-offs, not from machines.
Planning something similar?
Share a sample or a drawing and we will quote against a written specification, not against a photograph.