Case Study: Cabin Blower Supply for a delivery platform in Southern Africa
Cabin Blower for A delivery platform in Southern Africa
A delivery platform came to us with a cabin blower programme for Southern Africa. The brief was ordinary and unforgiving at the same time: a fixed launch window, a landed cost that had to survive freight and duty, and a part that had to match an existing sample. This case records what was specified, what went wrong in sampling and how the bulk order landed.
The starting point
- A specification nobody had written down
- Reorders that did not match the approved sample
- A fitment that looked right on paper and failed on the bench

What was specified
| Part | Cabin Blower |
|---|---|
| Client | A delivery platform |
| Market | Southern Africa |
| Volume | 10,000 pieces across 6 specifications |
| Base material | Carbon Steel |
| Sampling rounds | 4 |
| Delivery window | 6 weeks from PO to ex-factory |
| Compliance | SAE J431 |
How it was resolved
- The specification was rebuilt around Carbon Steel and the tolerance locked before bulk.
- A pre-production sample was approved and kept as the golden reference.
- Production ran with in-line inspection and a mid-run photo report.
- Cartons were packed to the client's own barcode and ratio specification.
- Documentation shipped with the goods instead of after them.

Result
- 10,000 pieces delivered inside the 6-week window.
- Unit cost held within 2.0% of the original quotation.
- Inspection-related rejection stayed under 1.0%.
- The specification is on file, so reorders reproduce the approved sample.
What we would repeat
Lock the material standard before sampling. Once the base changes, every downstream approval has to be redone and the calendar slips.
Planning something similar?
Send the part number, the annual volume and the target market, and we will come back with a specification and a sampling plan.



