Case Study: Roof Rack Supply for a supermarket chain in the Middle East
Source:Case /
Time:2026-09-18
Roof Rack for A supermarket chain in the Middle East
A supermarket chain came to us with a roof rack programme for the Middle East. The brief was ordinary and unforgiving at the same time: a fixed launch window, a landed cost that had to survive freight and duty, and a part that had to match an existing sample. This case records what was specified, what went wrong in sampling and how the bulk order landed.
The starting point
- A supplier who changed material without saying so
- Premature wear on the first batch
- Lead time that slipped twice before bulk started

What was specified
| Part | Roof Rack |
|---|---|
| Client | A supermarket chain |
| Market | the Middle East |
| Volume | 10,000 pieces across 2 specifications |
| Base material | Polypropylene |
| Sampling rounds | 2 |
| Delivery window | 4 weeks from PO to ex-factory |
| Compliance | ECE R90 |
How it was resolved
- The specification was rebuilt around Polypropylene and the tolerance locked before bulk.
- A pre-production sample was approved and kept as the golden reference.
- Production ran with in-line inspection and a mid-run photo report.
- Cartons were packed to the client's own barcode and ratio specification.
- Documentation shipped with the goods instead of after them.

Result
- 10,000 pieces delivered inside the 4-week window.
- Unit cost held within 4.5% of the original quotation.
- Inspection-related rejection stayed under 1.0%.
- The specification is on file, so reorders reproduce the approved sample.
What we would repeat
Keep one accountable owner on both sides. Most delays come from hand-offs, not from machines.
Planning something similar?
Share a sample or a drawing and we will quote against a written specification, not against a photograph.