Case Study: Strut Mount Supply for a fleet operator in South Asia
Source:Case /
Time:2026-09-18
Strut Mount for A fleet operator in South Asia
A fleet operator came to us with a strut mount programme for South Asia. The brief was ordinary and unforgiving at the same time: a fixed launch window, a landed cost that had to survive freight and duty, and a part that had to match an existing sample. This case records what was specified, what went wrong in sampling and how the bulk order landed.
The starting point
- A fitment that looked right on paper and failed on the bench
- Inconsistent hardness between lots
- A specification nobody had written down

What was specified
| Part | Strut Mount |
|---|---|
| Client | A fleet operator |
| Market | South Asia |
| Volume | 20,000 pieces across 4 specifications |
| Base material | Semi-Metallic Compound |
| Sampling rounds | 4 |
| Delivery window | 5 weeks from PO to ex-factory |
| Compliance | ECE R90 |
How it was resolved
- The specification was rebuilt around Semi-Metallic Compound and the tolerance locked before bulk.
- A pre-production sample was approved and kept as the golden reference.
- Production ran with in-line inspection and a mid-run photo report.
- Cartons were packed to the client's own barcode and ratio specification.
- Documentation shipped with the goods instead of after them.

Result
- 20,000 pieces delivered inside the 5-week window.
- Unit cost held within 1.5% of the original quotation.
- Inspection-related rejection stayed under 0.5%.
- The specification is on file, so reorders reproduce the approved sample.
What we would repeat
Approve a pre-production sample made from the actual bulk material. Substitute material behaves differently in service.