Case Study: Power Window Motor Supply for a rental company in West Africa
Power Window Motor for A rental company in West Africa
A rental company came to us with a power window motor programme for West Africa. The brief was ordinary and unforgiving at the same time: a fixed launch window, a landed cost that had to survive freight and duty, and a part that had to match an existing sample. This case records what was specified, what went wrong in sampling and how the bulk order landed.
The starting point
- A fitment that looked right on paper and failed on the bench
- Warranty claims traced back to a single lot
- Documentation that arrived after the container shipped

What was specified
| Part | Power Window Motor |
|---|---|
| Client | A rental company |
| Market | West Africa |
| Volume | 20,000 pieces across 3 specifications |
| Base material | Forged Aluminium |
| Sampling rounds | 3 |
| Delivery window | 10 weeks from PO to ex-factory |
| Compliance | CCC |
How it was resolved
- The specification was rebuilt around Forged Aluminium and the tolerance locked before bulk.
- A pre-production sample was approved and kept as the golden reference.
- Production ran with in-line inspection and a mid-run photo report.
- Cartons were packed to the client's own barcode and ratio specification.
- Documentation shipped with the goods instead of after them.

Result
- 20,000 pieces delivered inside the 10-week window.
- Unit cost held within 3.0% of the original quotation.
- Inspection-related rejection stayed under 0.5%.
- The specification is on file, so reorders reproduce the approved sample.
What we would repeat
Approve a pre-production sample made from the actual bulk material. Substitute material behaves differently in service.
Planning something similar?
Send the part number, the annual volume and the target market, and we will come back with a specification and a sampling plan.